Technical Deviation
Keep your deviations under control

For FIDIC contracts the Engineer role can be preformed by the Project Manager of a Project Management Company or it could be the Project Manager of the Employer (Company who develops and owns the project). Download the flow-chart (Power Point)

Technical deviations are deviations from drawings, specifications and other technical requirements.

Possible deviations should be proposed and agreed before they are implemented. In case they impact on cost and/or schedule then the change procedure shall be followed first.

Sometimes technical deviations are requested for work already performed incorrectly. Such situation can be either be corrected under redo obligation or can be accepted (if possible).

A Technical deviation is requested through a Technical Query form (free download).

Want to learn more, we can train & coach your team.

We offer with our partners a unique set of FIDIC training courses which range from FIDIC contract knowledge to Contract Management, Claim Management and Negotiation Training courses which are tailored around the FIDIC contract management roles.

Topics: contract kick-off, record keeping & filing, systems, communication, meetings, daily site reports, technical queries, technical deviations, site instructions, contract variations and claims, damage, reports, KPIs, non conformities, insurance, completion, Taking-Over, testing and contract close-out.